Alappuzha bypass project in limbo

Delay in constructing two rail overbridges at Malikamukku and Kuthirapanthy stalls project

October 22, 2018 11:23 pm | Updated 11:24 pm IST - ALAPPUZHA

The elevated stretch of the Alappuzha bypass

The elevated stretch of the Alappuzha bypass

The Alappuzha bypass project is not likely to be opened to traffic this year. Although 96% of the project has been completed, construction of two rail overbridges (ROBs) at Malikamukku and Kuthirapanthy are still pending.

Sources said that steel girders, needed for the construction of ROBs had been brought to Alappuzha but work was yet to commence. “At present we cannot provide a timeline for the completion of the project. The bypass will be commissioned only after constructing ROBs,” a Public Works Department official told The Hindu .

Sources said that it was very unlikely the bypass would be opened to traffic this year.

Railways blamed

Meanwhile, representatives of the consortium comprising RDS Project Ltd and Cheriyan Varkey Construction Company blamed the Railways for the delay. “We are awaiting a final safety approval from the Railways. Once the nod is received the construction of ROBs will be completed without any further delay,” said a representative of the consortium.

The bypass work, which got under way on April 10, 2015 was originally set to be completed in September 2017. However, the project got delayed on account of various reasons and the deadline was initially extended to May 28, 2018 and further to August 31.

Earlier this month, Public Works Minister G. Sudhakaran said that the deadline for the completion of the project had ended on August 31 and government would not extend it any further.

He added that the government would not announce a new date for the completion of the project.

Bringing relief

Once completed, the bypass is expected to bring relief to Alappuzha town, which has been witnessing traffic snarls on its arterial roads for several years now.

With the new bypass, the town would be able to breath a little easier.

And that would also ensure smooth movement of traffic between the State capital and the State’s commercial hub and beyond.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.