Nashik: Pre-monsoon works still incomplete in city

Although the monsoon has arrived, Nashik Municipal Corporation (NMC) is yet to complete the pre-monsoon works like cleaning of nullahs, drainage chambers and storm water lines.
Nashik: Pre-monsoon works still incomplete in city
Nashik Municipal Corporation (File Photo)
NASHIK: Although the monsoon has arrived, the Nashik Municipal Corporation (NMC) is yet to complete the pre-monsoon works like cleaning of nullahs, drainage chambers and storm water lines.
NMC officials said that over 80% of the pre-monsoon works have been completed so far and the remaining 20% of the works are to be completed within a week or two.
NMC has cleaned nullahs with a length of 47km and it is yet to clean nullhas with length of 4km in the city.

Moreover, the civic body has cleaned 11,145 manholes on drainage lines and remaining 2,800 manholes are yet to be completed.
The civic administration has cleaned stormwater lines with a length of 43 kms and it is yet to complete storm water lines with a length of 15km.